NEC4 · ECC Option C 54.1 (Option D 54.5)
share range
A band of the Price for Work Done to Date as a percentage of the total of the Prices. Each band has its own Contractor's share percentage.
On the Aldermere project
Aldermere's share is 50% between 90% and 110% of the total of the Prices, and 25% outside.
Also written as
- share ranges
- Contractor's share percentage
- share percentage
Lessons that teach this
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 12 · 5 min Members
- Work out the Contractor's shareWork out the Contractor's sharePayment and Defined Cost · Module 12 · 6 min Members
- Build the final amount due and the final paymentBuild the final amount due and the final paymentPayment and Defined Cost · Module 12 · 6 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 3 · 6 min Members
- Why Option C is not cost-plusPayment and Defined Cost · Module 1 · 6 min Free
- Target Options C and DTarget Options C and DContract Preparation · Module 3 · 5 min Members
Where you meet it
- Module 12: Target contracts under Options C and DPractitioner Course
- Module 10: Disallowed Cost, ground by groundPayment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost