NEC4 · ECC Option C 11.2(31)
accrual
A cost entered in the accounts before it is paid. It counts as Defined Cost only when paid, or when the Project Manager forecasts payment before the next assessment date.
Also written as
- accruals
Lessons that teach this
- Agency staff, timesheets and bonusesAgency staff, timesheets and bonusesPayment and Defined Cost · Module 5 · 5 min Members
- Test each audit finding against its evidenceTest each audit finding against its evidencePayment and Defined Cost · Module 11 · 6 min Members
Where you meet it
- Module 5: PeoplePayment and Defined Cost
- Module 11: Records, audits and clawbackPayment and Defined Cost