NEC4 · ECC 50.6
clawback
Getting back money already certified and paid, often after an audit finds cost that was not Defined Cost. Under the ECC it comes off a later payment.
Also written as
- claw back
Lessons that teach this
- Test each audit finding against its evidenceTest each audit finding against its evidencePayment and Defined Cost · Module 11 · 6 min Members
Where you meet it
- Module 11: Records, audits and clawbackPayment and Defined Cost