FIDIC 2017 · FIDIC 1.1.11
Contract Agreement
The formal agreement both Parties sign under Sub-Clause 1.6, within 35 days after the Letter of Acceptance unless agreed otherwise. It ranks first among the documents.
“the agreement entered into by both Parties” (FIDIC 1.1.11)
On the Aldermere project
The Aldermere Contract Agreement was signed on 5 January 2026, within the 35 days.
Lessons that teach this
- When documents conflictNEC4 vs FIDIC 2017 · Module 1 · 7 min Free