NEC4 · ECC Option C
Option C
The target Option with an activity schedule. Payment is Defined Cost plus the Fee, and the Contractor shares any saving or overrun against the total of the Prices.
On the Aldermere project
Aldermere uses Option C. The final saving of GBP 272,000 gave Merrow Vale a share of GBP 136,000.
Lessons that teach this
- The target and what moves itThe target and what moves itPractitioner Course · Module 12 · 5 min Members
- The Contractor's shareThe Contractor's sharePractitioner Course · Module 12 · 5 min Members
- Forecasts and agreeing Defined CostForecasts and agreeing Defined CostPractitioner Course · Module 12 · 5 min Members
- Target Options C and DTarget Options C and DContract Preparation · Module 3 · 5 min Members
- Options E and F, and choosing yoursOptions E and F, and choosing yoursContract Preparation · Module 3 · 5 min Members
- Share, cost checks, PSC and TSCShare, cost checks, PSC and TSCContract Preparation · Module 3 · 6 min Members
- Defined Cost is a listDefined Cost is a listPayment and Defined Cost · Module 4 · 6 min Members
- Test the instruction against the ScopeValid compensation events · Module 1 · 6 min Free
Where you meet it
- Module 12: Target contracts under Options C and DPractitioner Course
- Module 3: How the main Options pay the ContractorContract Preparation