NEC4 · ECS 11.2(16)
Subcontract Completion Date
The date the Subcontractor must complete by. It starts as the date in the Subcontract Data and moves only under the subcontract.
“the subcontract completion date unless later changed in accordance with the subcontract” (ECS 11.2(16))
On the Aldermere project
CE019 moved Cobalt's Subcontract Completion Date from 5 March 2027 to 10 March 2027.