NEC4 · ECC 35.1
take over
When the Client takes the works into its care and use. This is normally within two weeks of Completion. Using a part early usually counts as taking it over.
On the Aldermere project
Aldermere Water took over the works on 26 May 2027, the day of Completion.
Also written as
- taken over
- takes over
- took over
Lessons that teach this
- Completion, Key Dates and take overCompletion, Key Dates and take overPractitioner Course · Module 13 · 5 min Members
- Delay damages and qualityDelay damages and qualityPractitioner Course · Module 13 · 5 min Members
- Correcting Defects and the Defects CertificateCorrecting Defects and the Defects CertificatePractitioner Course · Module 13 · 6 min Members
- Design or build, and who insuresDesign or build, and who insuresCase Law · Module 5 · 6 min Members
- Defects and the defects dateDefects and the defects dateCase Law · Module 5 · 6 min Members
- Handing over to maintenanceHanding over to maintenanceContract Preparation · Module 11 · 6 min Members
- Retention under X16Retention under X16Payment and Defined Cost · Module 3 · 5 min Members
- Delay damages under X7Delay damages under X7Payment and Defined Cost · Module 3 · 6 min Members
Where you meet it
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 5: Design, Defects and insuranceCase Law
- Module 11: Your contract strategyContract Preparation