NEC4 · ECC 11.2(11)
Key Date
A date by which part of the work must meet a stated Condition, set in the Contract Data. Missing it can make the Contractor pay the Client's extra costs.
“the date by which work is to meet the Condition stated” (11.2(11))
On the Aldermere project
Key Date 1 is 30 September 2026. Its Condition was met on 25 September 2026.
Also written as
- Key Dates
- key date
Lessons that teach this
- Completion, Key Dates and take overCompletion, Key Dates and take overPractitioner Course · Module 13 · 5 min Members
- Key Dates, take over and DefectsKey Dates, take over and DefectsContract Preparation · Module 6 · 5 min Members
- Reading and changing the wordsPractitioner Course · Module 1 · 5 min Free
- Packaging and the timescalePackaging and the timescaleContract Preparation · Module 2 · 6 min Members
- When a reply is lateWhen a reply is latePractitioner Course · Module 4 · 6 min Members
- What to warn of, and howWhat to warn of, and howPractitioner Course · Module 5 · 6 min Members
- Duties beside the workDuties beside the workPractitioner Course · Module 6 · 5 min Members
- What counts as a compensation eventWhat counts as a compensation eventPractitioner Course · Module 8 · 5 min Members
Where you meet it
- Module 1: How the ECC fits togetherPractitioner Course · Free
- Module 2: The procurement questions to answer firstContract Preparation