time risk allowance
Time the Contractor builds into a programme for its own risks, such as normal bad weather. Each programme must show it.
On the Aldermere project
Dana did not accept the first programme on 3 February 2026, partly because it showed no time risk allowances.
Also written as
- time risk allowances
Lessons that teach this
- What a programme must showWhat a programme must showPractitioner Course · Module 7 · 5 min Members
- Reply, refusal and silenceReply, refusal and silencePractitioner Course · Module 7 · 5 min Members
- Checking the target and the programmeChecking the target and the programmeContract Preparation · Module 9 · 5 min Members
- What goes on and what comes offWhat goes on and what comes offPayment and Defined Cost · Module 3 · 6 min Members
- What the programme must showWhat the programme must showNEC4 vs FIDIC 2017 · Module 2 · 5 min Members
- The tender programmeThe tender programmeContract Preparation · Module 10 · 5 min Members
Where you meet it
- Module 7: The programmePractitioner Course
- Module 9: Tender assessment and subcontractsContract Preparation